Door Hardware Schedule: Procurement and Approval Guide

A quote built from hardware photos or a generic bill of materials is not a project hardware schedule. The purchasing file must connect each opening number on the drawings to a door and frame, an approved hardware set and the preparation needed by every component. That link prevents the lock from arriving with the wrong backset, the closer from conflicting with the frame, or the fire-rated opening from being assembled from incompatible items.
Build an opening-by-opening baseline
Start with the latest architectural drawings, door and frame schedule, door elevations, specifications, life-safety information and access-control design. Assign one controlled row to every opening, including inactive leaves and paired doors. Do not merge doors merely because their appearance is similar.
| Field | What to record | Procurement risk if missing |
|---|---|---|
| Opening identity | Door number, building, floor, room/space and drawing reference | Hardware and delivered doors cannot be traced to location |
| Geometry | Single/pair, width, height, thickness, handing, swing and degree of opening | Wrong preparations, closer arm, hinge loading or installation clearance |
| Door and frame | Material, construction, frame type, anchors, wall condition and finish | Fasteners and hardware may not suit the substrate or edge construction |
| Performance | Fire/smoke rating, acoustic or weather requirement, egress role and project jurisdiction | Components may not be permitted within the required assembly |
| Hardware assignment | Hardware set number, lock function, keying group, closer, seals, threshold and stop | Quotation does not contain a complete working opening |
| Electrical interface | Access control, electric lock/strike, monitor, power transfer, operator, voltage and cabling responsibility | Late site cutting, incompatible power or missing control interfaces |
| Approval status | Schedule revision, submittal revision, comment status and release date | Factory builds from a superseded document |
If the project also imports the doors, use the interior door specification and QC guide to coordinate leaf construction, frames, finishes and hardware preparation. The schedule in this article governs opening-level coordination; it does not replace the door product specification.
Turn each function into a complete hardware set
A hardware set should describe the complete opening, not just the lock. Typical line items include hinges or pivots, lock/latch, cylinder, closer, exit device where required, stops, protection plates, seals, threshold, flush bolts or coordinator for pairs, signage and access-control components. Quantities, functions, finishes and manufacturer references belong on the approved set.
| Component group | Questions before approval | Interface to verify |
|---|---|---|
| Hinges, pivots and continuous hinges | Door mass, width, frequency, bearing type, quantity, finish and security features? | Door/frame reinforcement, screw or weld preparation and clearances |
| Locks, latches and cylinders | Function, handing, backset, door thickness, keyway, lever, strike and master-key requirements? | Edge/face preparation, frame strike, access control and keying schedule |
| Closers and operators | Mounting side, arm type, opening angle, power range, hold-open restrictions and control interface? | Frame/head clearance, reinforcement, stop location and accessibility requirements |
| Exit devices | Door type, fire-exit or panic application, trim, dogging, latch monitoring and power? | Door construction, pair coordination, strikes, egress design and listed assembly |
| Seals, thresholds and protection | Smoke, acoustic, weather, accessibility and floor-finish conditions? | Bottom gap, finished floor level, closer force and fire/smoke assembly |
| Electrified hardware | Fail-safe/fail-secure function, voltage, current, monitoring, cable path and emergency behavior? | Security drawings, fire alarm, power supplies, door loops and commissioning responsibility |
For component sourcing and cycle-test questions, see the door hardware manufacturer and quality-control guide. It complements the schedule by examining locks, hinges and durability; it does not decide which hardware belongs on each project opening.
Separate code decisions from supplier selection
The project architect, code consultant and authority having jurisdiction determine the applicable requirements. A sourcing company or overseas factory should not redesign a life-safety opening through an informal substitution.
For U.S. accessible routes, the ADA Standards published by the U.S. Access Board include requirements for door and gate hardware, including operability and mounting ranges. Record the approved mounting height and hardware function on the schedule and shop drawings rather than relying on a general “ADA” note.
Fire-rated openings must be treated as assemblies. The UL Doors, Windows and Related Hardware Application Guide explains that doors, frames, glazing, hardware and accessories may be certified in different product categories and must be used within their intended scope and installation instructions. UL also distinguishes fire-exit hardware for fire doors from panic hardware intended only for non-rated exit doors.
The 2022 edition of NFPA 80 includes chapters for swinging doors with builders hardware and fire-door hardware. The effective project edition and local amendments must be confirmed by the design team or authority. Never replace a specified listed component solely because another item looks equivalent.
Run a controlled submittal and release sequence
Issue one supplier enquiry package with the same document register to all bidders. Require deviations to be declared line by line. After technical comparison, the supplier or hardware consultant prepares the detailed schedule, product data and opening-specific sets for design review. Commercial release occurs only after comments are closed.
| Gate | Required output | Release condition |
|---|---|---|
| 1. Bid baseline | Door schedule, hardware sets, specification, drawings, finish and compliance requirements | All bidders price the same revision and list exclusions |
| 2. Technical alignment | Opening-by-opening compliance matrix and requests for information | Conflicts in handing, rating, function and preparation are resolved |
| 3. Submittal approval | Product data, certificates/listings where required, samples, finish board and coordinated schedule | Design team status permits procurement; comments are incorporated |
| 4. Manufacturing release | Approved revision, door/frame preparation drawings, keying direction and electrical interface schedule | No unresolved dependency affects factory work |
| 5. Pre-shipment release | Inspection results, packing list by opening/zone, labels and closeout documents | Quantities, function, finish, traceability and documents comply |
Coordinate door, frame and hardware preparation
Hardware cannot be reviewed independently from the door and frame. For every lock, closer, hinge, flush bolt, coordinator, strike and electrical device, verify the cutout, reinforcement, conduit or cable path, fixing type and installation clearance. A factory drawing should identify dimensions from consistent datums and reference the opening and approved hardware model.
Wood doors need confirmed core and blocking where hardware loads require it; the wooden door project QC guide covers core, finish and manufacturing controls. Aluminum doors require compatible profiles, reinforcement, glazing and drainage; use the aluminum door sourcing guide for those product-specific checks.
Inspect and pack by opening, not by loose SKU
Before shipment, sample assembled openings or representative door/frame/hardware mock-ups where project risk justifies it. Check handing, latch engagement, lever and cylinder function, closer operation, clearances, finish, fastener security and electrical signals. Verification should follow the approved schedule and manufacturer instructions, not an inspector’s memory.
Pack hardware sets by opening number or clearly controlled zone. Each package should carry a durable identifier linked to the packing list, while master keys and security-sensitive records follow an agreed custody procedure. Separate finish-sensitive pieces, protect long thresholds and seals, and retain a discrepancy log for shortages or substituted items.
Keep the schedule alive through installation and handover
Site changes should update the controlled schedule, not remain in email threads. Record approved substitutions, revised door numbers, keying changes, access-control interfaces and final installed models. At handover, provide the as-built schedule, keying records, certificates, test/commissioning evidence, maintenance instructions and spare-parts list required by the contract.
A disciplined schedule turns a complex door package into auditable opening-level decisions. It also gives the buyer a clear basis for quotation comparison, factory release, inspection, installation and later maintenance without treating doors, frames and hardware as unrelated purchases.
Coordinate hardware preparation with verified site conditions. The door opening field survey guide shows how to record handing, swing, wall construction, floor level and clear-passage constraints before production release.